Mechanics’ Lien Claim Defeated Where Contractor Fails to Provide Proper Contractor Affidavit

Pyramid Development, LLC v. DuKane Precast, 2014 IL App (2d) 131131, vividly illustrates the importance of diligent record-keeping practices on construction projects and the dire financial consequences that can flow from a failure to do so.  It emphasizes how crucial it is for a contractor to comply with Section 5 of the mechanic’s lien act – …

Contractor’s Failure to Provide Sworn Statement Dooms Mechanics Lien Suit

A contractor lost its nearly $400,000 mechanics’ lien when it failed to serve a “Section 5 statement”, which lists subcontractors and amounts owed and owing, after the property owner requested one.  770 ILCS 60/5 (the “Lien Act”). In Cityline Construction v. Roberts, 2014 IL App (1st) 130730, the parties entered into an oral contract for fire restoration work.  The plaintiff …

General Contractor’s Bankruptcy Filing Means Extra Time For Subcontractor To File Lien Suit

Section 34 of the Illinois Mechanics Lien Act (770 ILCS 60/34) presents a way for an owner to quickly dispose of a contractor’s lien recorded against his/her property. Typically, the owner serves the Section 34 notice and the contractor must either sue to foreclose its lien within 30 days or it loses the lien. But what if after …