Sole Proprietor’s Mechanics Lien OK Where Lien Recorded in His Own Name (Instead of Business Name) – IL Court

 

While the money damages involved in Gerlick v. Powroznik (2017 IL App (1st) 153424-U) is low, the unpublished case provides some useful bullet points governing construction disputes.  Chief among them include what constitutes substantial performance, the recovery of contractual “extras,” and the standards governing attorney fee awards under Illinois’s mechanics lien statute.

The plaintiff swimming pool installer sued the homeowner defendants when they failed to fully pay for the finished pool.  The homeowners claimed they were justified in short-paying the plaintiff due to drainage and other mechanical problems.

After a bench trial, the court entered judgment for the pool installer for just over $20K and denied his claim for attorneys’ fees under the Act.  Both parties appealed; the plaintiff appealed the denial of attorneys’ fees while the defendants appealed the underlying judgment.

Held: Affirmed

Reasons:

A breach of contract plaintiff in the construction setting must prove it performed in a reasonably workmanlike manner.  In finding the plaintiff sufficiently performed, the Court rejected the homeowners’ argument that plaintiff failed to install two drains.  The Court viewed drain installation as both ancillary to the main thrust of the contract and not feasible with the specific pool model (the King Shallow) furnished by the plaintiff.

The Court also affirmed the trial court’s mechanic’s lien judgment for the contractor.  In Illinois, a mechanics lien claimant must establish (1) a valid contract between the lien claimant and property owner (or an agent of the owner), (2) to furnish labor, services or materials, and (3) the claimant performed or had a valid excuse of non-performance.  (¶ 37)

A contractor doesn’t have to perform flawlessly to avail itself of the mechanics’ lien remedy: all that’s required is he perform the main parts of a contract in a workmanlike manner.  Where a contractor substantially performs, he can enforce his lien up to the amount of work performed with a reduction for the cost of any corrections to his work.

The owners first challenged the plaintiff’s mechanics’ lien as facially defective.  The lien listed plaintiff (his first and last name) as the claimant while the underlying contract identified only the plaintiff’s business name (“Installation Services & Coolestpools.com”) as the contracting party.  The Court viewed this discrepancy as trivial since a sole proprietorship or d/b/a has no legal identity separate from its operating individual.  As a consequence, plaintiff’s use of a fictitious business name was not enough to invalidate the mechanic’s lien.

The Court also affirmed the trial court’s denial of plaintiff’s claim for extra work in the amount of $4,200.  A contractor can recover “extras” to the contract where (1) the extra work performed or materials furnished were outside the scope of the contract, (2) the extras were furnished at owner’s request, (3) the owner, by words or conduct, agreed to compensate the contractor for the extra work, (4) the contractor did not perform the extra work voluntarily, and (5) the extra work was not necessary through the fault of the contractor.

The Court found there was no evidence that the owners asked the plaintiff to perform extra work – including cleaning the pool, inspecting equipment and fixing the pool cover.  As a result, the plaintiff did not meet his burden of proving his entitlement to extras recovery. (¶¶ 39-41).

Lastly, the Court affirmed the trial court’s denial of attorneys’ fees to the plaintiff.  A mechanics’ lien claimant must prove that an owner’s failure to pay is “without just cause or right;” a phrase meaning not “well-grounded in fact and warranted by existing law or a good faith argument for the extension, modification, or reversal of existing law.” 770 ILCS 60/17(a).  Here, because there was evidence of a good faith dispute concerning the scope and quality of plaintiff’s pool installation, the Court upheld the trial court’s denial of plaintiff’s fee award attempt.

Afterwords:

1/ A contractor doesn’t have to perform perfectly in order to win a breach of contract or mechanics’ lien claim.  So long as he performs in a workmanlike manner and substantially completes the hired-for work, he can recover under both legal theories.

2/ A sole proprietor and his fictitious business entity are one and the same.  Because of this business owner – d/b/a identity, the sole proprietor can list himself as the contractor on a lien form even where the underlying contract lists only his business name.

 

 

New York’s Public Policy On Construction Dispute Venue Trumps Illinois Forum-Selection Clause – IL 2d Dist.

Dancor Construction, Inc. v. FXR Construction, Inc., 2016 IL App (1st) 150839 offers a nuanced discussion of forum selection clauses and choice-of-law principles against the backdrop of a multi-jurisdictional construction dispute.

The plaintiff general contractor (GC) sued a subcontractor (Sub) in Illinois state court for breach of a construction contract involving New York (NY) real estate.  The contract had a forum selection clause that pegged Kane County Illinois (IL) as the forum for any litigation involving the project.  

The trial court agreed with the Sub’s argument that the forum-selection clause violated NY public policy (that NY construction litigation should be decided only in NY) and dismissed the GC’s suit.  Affirming, the Second District discusses the key enforceability factors for forum-selection clauses when two or more jurisdictions are arguably the proper venue for a lawsuit.

Public Policy – A Statutory Source

The Court first observed that IL’s and NY’s legislatures both addressed the proper forum for construction-related lawsuits.  Section 10 of Illinois’ Building and Construction Contract Act, 815 ILCS 665/10, voids any term of an IL construction contract that subjects the contract to the laws of another state or that requires any litigation concerning the contract to be filed in another state.

NY’s statute parallels that of Illinois.  NY Gen. Bus. Law Section 757(1) nullifies construction contract terms that provide for litigation in a non-New York forum or that applies (non-) NY law.

Since a state’s public policy is found in its published statute (among other places), NY clearly expressed its public policy on the location for construction litigation.

Forum Selection and Choice-of-Law Provisions

An IL court can void a forum-selection clause where it violates a fundamental IL policy.  A forum-selection clause is prima facie valid unless the opposing side shows that enforcement of the clause would be unreasonable.

A forum-selection clause reached by parties who stand at arms’ length should be honored unless there is a compelling and countervailing reason not to enforce it. (¶ 75)

A choice-of-law issue arises where there is an actual conflict between two states’ laws on a given issue and it isn’t clear which state’s law governs.  Here, IL and NY were the two states with ostensible interests in the lawsuit.  There was also a plain conflict between the states’ laws: the subject forum-selection clause was prima facie valid in IL while it plainly violated NY law.

Which Law Applies – NY or IL?

Illinois follows Section 187 of the Restatement (Second) of Conflicts of Laws (1971) which provides that the laws of a state chosen by contracting parties will apply unless (1) the chosen state has no substantial relationship to the parties or the transaction and there is no other reasonable basis for the parties’ choice, or (2) application of the law of the chosen state would violate a fundamental policy of a state that has a materially greater interest than the chosen state on a given issue.

The Court found the second exception satisfied and applied NY law.  

Section 757 of NY’s business statute clearly outlaws forum-selection clauses that provide for the litigation of NY construction disputes in foreign states.  As a result, the contract’s forum clause clearly violates NY’s public policy of having NY construction disputes decided in NY.

The question then became which state, NY or IL, had the greater interest in the forum-selection clause’s enforcement?  Since NY was the state where the subcontractor resided, where the building (and contract’s finished product) was erected and the contract ultimately performed, the Court viewed NY as having a stronger connection.  Since allowing the case to proceed in IL clearly violated NY’s public policy, the Court affirmed dismissal of the GC’s lawsuit.

Afterwords:

Forum selection clauses are prima facie valid but not inviolable.  Where a chosen forum conflicts with a public policy of another state, there is a conflict of laws problem.  

The Court will then analyze which state has a more compelling connection to the case.  Where the state with both a clear public policy on the issue also has a clearer nexus to the subject matter of the lawsuit, the Court will apply that state’s (the one with the public policy and closer connection) law on forum-selection clauses.

 

Pay-When-Paid Clause in Subcontract Not Condition Precedent to Sub’s Right to Payment – IL Court

Pay-if-paid and pay-when-paid clauses permeate large construction projects

In theory, the clauses protect a contractor from downstream liability where its upstream or hiring party (usually the owner) fails to pay.

Beal Bank Nevada v. Northshore Center THC, LLC, 2016 IL App (1st) 151697 examines the fine-line distinction between PIP and PWP contract terms. a lender sued to foreclose

The plaintiff lender sued to foreclose commercial property and named the general contractor (GC) and subcontractor (Sub) as defendants.  The Sub countersued to foreclose its nearly $800K lien and added a breach of contract claims against the GC.

In its affirmative defense to the Sub’s claim, the GC argued that payment from the owner to the GC was a condition precedent to the GC’s obligation to pay the Sub.  The trial court agreed with the GC and entered summary judgment for the GC.  The Sub appealed.

Result: Reversed.

Reasons:

The Subcontract provided the GC would pay the Sub upon certain events and arguably (it wasn’t clear) required the owner’s payment to the GC as a precondition to the GC paying the Sub.  The GC seized on this owner-to-GC payment language as grist for its condition precedent argument: that if the owner didn’t pay the GC, it (the GC) didn’t have to pay the Sub.

Under the law, a condition precedent is an event that must occur or an act that must be performed by one party to an existing contract before the other party is obligated to perform.  Where a  condition precedent is not satisfied, the parties’ contractual obligations cease.

But conditions precedent are not favored.  Courts will not construe contract language that’s arguably a condition precedent where to do so would result in a forfeiture (a complete denial of compensation to the performing party). (¶ 23)

The appeals court rejected the GC’s condition precedent argument and found the Subcontract had a PWP provision.  For support, the court looked to the contractual text and noted it attached two separate payment obligations to the GC – one was to pay the Sub upon “full, faithful and complete performance,”; the other, to make payment in accordance with Article 5 of the Subcontract which gave the GC a specific amount of time to pay the Sub after the GC received payment from the owner.

The Court reconciled these sections as addressing the amounts and timing of the GC’s payments; not whether the GC had to pay the Sub in the first place. (¶¶ 19-20)

Further support for the Court’s holding that there was no condition precedent to the GC’s obligation to pay the Sub lay in another Subcontract section that spoke to “amounts and times of payments.”  The presence of this language signaled that it wasn’t a question of if the GC had to pay the Sub but, instead, when it paid.

In the end, the Court applied the policy against declaring forfeitures: “[w]ithout clear language indicating the parties’ intent that the Subcontractor would assume the risk of non-payment by the owner, we will not construe the challenged language…..as a condition precedent.” (¶ 23)

Since the Subcontract was devoid of “plain and unambiguous” language sufficient to overcome the presumption against a wholesale denial of compensation, the Court found that the Subcontract contained pay-when-paid language and that there was no condition precedent to the Sub’s entitlement to payment from the GC.

Take-aways

Beal Bank provides a solid synopsis of pay-if-paid and pay-when-paid clauses.  PIPs address whether a general contractor has to pay a subcontractor at all while PWPs speak to the timing of a general’s payment to a sub.

The case also re-emphasizes that Section 21(e) of the Illinois Mechanics Lien Act provides that the presence of a PIP or PWP contract term is no defense to a mechanics lien claim (as opposed to garden-variety breach of contract claim).