Pay-When-Paid Clause in Subcontract Not Condition Precedent to Sub’s Right to Payment – IL Court

Pay-if-paid and pay-when-paid clauses permeate large construction projects

In theory, the clauses protect a contractor from downstream liability where its upstream or hiring party (usually the owner) fails to pay.

Beal Bank Nevada v. Northshore Center THC, LLC, 2016 IL App (1st) 151697 examines the fine-line distinction between PIP and PWP contract terms. a lender sued to foreclose

The plaintiff lender sued to foreclose commercial property and named the general contractor (GC) and subcontractor (Sub) as defendants.  The Sub countersued to foreclose its nearly $800K lien and added a breach of contract claims against the GC.

In its affirmative defense to the Sub’s claim, the GC argued that payment from the owner to the GC was a condition precedent to the GC’s obligation to pay the Sub.  The trial court agreed with the GC and entered summary judgment for the GC.  The Sub appealed.

Result: Reversed.

Reasons:

The Subcontract provided the GC would pay the Sub upon certain events and arguably (it wasn’t clear) required the owner’s payment to the GC as a precondition to the GC paying the Sub.  The GC seized on this owner-to-GC payment language as grist for its condition precedent argument: that if the owner didn’t pay the GC, it (the GC) didn’t have to pay the Sub.

Under the law, a condition precedent is an event that must occur or an act that must be performed by one party to an existing contract before the other party is obligated to perform.  Where a  condition precedent is not satisfied, the parties’ contractual obligations cease.

But conditions precedent are not favored.  Courts will not construe contract language that’s arguably a condition precedent where to do so would result in a forfeiture (a complete denial of compensation to the performing party). (¶ 23)

The appeals court rejected the GC’s condition precedent argument and found the Subcontract had a PWP provision.  For support, the court looked to the contractual text and noted it attached two separate payment obligations to the GC – one was to pay the Sub upon “full, faithful and complete performance,”; the other, to make payment in accordance with Article 5 of the Subcontract which gave the GC a specific amount of time to pay the Sub after the GC received payment from the owner.

The Court reconciled these sections as addressing the amounts and timing of the GC’s payments; not whether the GC had to pay the Sub in the first place. (¶¶ 19-20)

Further support for the Court’s holding that there was no condition precedent to the GC’s obligation to pay the Sub lay in another Subcontract section that spoke to “amounts and times of payments.”  The presence of this language signaled that it wasn’t a question of if the GC had to pay the Sub but, instead, when it paid.

In the end, the Court applied the policy against declaring forfeitures: “[w]ithout clear language indicating the parties’ intent that the Subcontractor would assume the risk of non-payment by the owner, we will not construe the challenged language…..as a condition precedent.” (¶ 23)

Since the Subcontract was devoid of “plain and unambiguous” language sufficient to overcome the presumption against a wholesale denial of compensation, the Court found that the Subcontract contained pay-when-paid language and that there was no condition precedent to the Sub’s entitlement to payment from the GC.

Take-aways

Beal Bank provides a solid synopsis of pay-if-paid and pay-when-paid clauses.  PIPs address whether a general contractor has to pay a subcontractor at all while PWPs speak to the timing of a general’s payment to a sub.

The case also re-emphasizes that Section 21(e) of the Illinois Mechanics Lien Act provides that the presence of a PIP or PWP contract term is no defense to a mechanics lien claim (as opposed to garden-variety breach of contract claim).