Pay-When-Paid Clause in Subcontract Not Condition Precedent to Sub’s Right to Payment – IL Court

Pay-if-paid and pay-when-paid clauses permeate large construction projects

In theory, the clauses protect a contractor from downstream liability where its upstream or hiring party (usually the owner) fails to pay.

Beal Bank Nevada v. Northshore Center THC, LLC, 2016 IL App (1st) 151697 examines the fine-line distinction between PIP and PWP contract terms. a lender sued to foreclose

The plaintiff lender sued to foreclose commercial property and named the general contractor (GC) and subcontractor (Sub) as defendants.  The Sub countersued to foreclose its nearly $800K lien and added a breach of contract claims against the GC.

In its affirmative defense to the Sub’s claim, the GC argued that payment from the owner to the GC was a condition precedent to the GC’s obligation to pay the Sub.  The trial court agreed with the GC and entered summary judgment for the GC.  The Sub appealed.

Result: Reversed.

Reasons:

The Subcontract provided the GC would pay the Sub upon certain events and arguably (it wasn’t clear) required the owner’s payment to the GC as a precondition to the GC paying the Sub.  The GC seized on this owner-to-GC payment language as grist for its condition precedent argument: that if the owner didn’t pay the GC, it (the GC) didn’t have to pay the Sub.

Under the law, a condition precedent is an event that must occur or an act that must be performed by one party to an existing contract before the other party is obligated to perform.  Where a  condition precedent is not satisfied, the parties’ contractual obligations cease.

But conditions precedent are not favored.  Courts will not construe contract language that’s arguably a condition precedent where to do so would result in a forfeiture (a complete denial of compensation to the performing party). (¶ 23)

The appeals court rejected the GC’s condition precedent argument and found the Subcontract had a PWP provision.  For support, the court looked to the contractual text and noted it attached two separate payment obligations to the GC – one was to pay the Sub upon “full, faithful and complete performance,”; the other, to make payment in accordance with Article 5 of the Subcontract which gave the GC a specific amount of time to pay the Sub after the GC received payment from the owner.

The Court reconciled these sections as addressing the amounts and timing of the GC’s payments; not whether the GC had to pay the Sub in the first place. (¶¶ 19-20)

Further support for the Court’s holding that there was no condition precedent to the GC’s obligation to pay the Sub lay in another Subcontract section that spoke to “amounts and times of payments.”  The presence of this language signaled that it wasn’t a question of if the GC had to pay the Sub but, instead, when it paid.

In the end, the Court applied the policy against declaring forfeitures: “[w]ithout clear language indicating the parties’ intent that the Subcontractor would assume the risk of non-payment by the owner, we will not construe the challenged language…..as a condition precedent.” (¶ 23)

Since the Subcontract was devoid of “plain and unambiguous” language sufficient to overcome the presumption against a wholesale denial of compensation, the Court found that the Subcontract contained pay-when-paid language and that there was no condition precedent to the Sub’s entitlement to payment from the GC.

Take-aways

Beal Bank provides a solid synopsis of pay-if-paid and pay-when-paid clauses.  PIPs address whether a general contractor has to pay a subcontractor at all while PWPs speak to the timing of a general’s payment to a sub.

The case also re-emphasizes that Section 21(e) of the Illinois Mechanics Lien Act provides that the presence of a PIP or PWP contract term is no defense to a mechanics lien claim (as opposed to garden-variety breach of contract claim).

General Contractor Insolvency, Not Owner Recourse, is Key Implied Warranty of Habitability Test – IL First Dist.

In Sienna Court Condominium Association v. Champion Aluminum Corporation, 2017 IL App (1st) 143364, the First District addressed two important issues of common law and statutory corporate law.  It first considered when a property owner could sue the subcontractor of a defunct general contractor where there was no contractual relationship between the owner and subcontractor and then examined when a defunct limited liability company (LLC) could file a lawsuit in the LLC’s name.

The plaintiff condo association sued the developer, general contractor (“GC”) and subcontractors for various building defects.  The subcontractors moved to dismiss the association’s claims on the ground that they couldn’t be liable for breaching the implied warranty of habitability if the plaintiff has possible recourse from the defunct GC’s insurer.

The trial court denied the subcontractors’ motion and they appealed.

Affirming denial of the subcontractors’ motions, the First District considered whether a homeowner’s implied warranty claim could proceed against the subcontractors of an insolvent GC where (1) the plaintiff had a potential source of recovery from the GC’s insurer or (2) the plaintiff had already recovered monies from a warranty fund specifically earmarked for warranty claims.

The court answered “yes” (plaintiff’s suit can go forward against the subs) on both counts. It held that when deciding whether a plaintiff can sue a subcontractor for breach of implied warranty of habitability, the focus is whether or not the GC is insolvent; not whether plaintiff can possibly recover (or even has recovered) from an alternate source (like a dissolved GC’s insurer).

For precedential support, the Court looked to 1324 W. Pratt Condominium Ass’n v. Platt Construction Group,   2013 IL App (1st) 130744 where the First District allowed a property buyer’s warranty claims versus a subcontractor where the general contractor was in good corporate standing and had some assets.  The court held that an innocent purchaser can sue a sub where the builder-seller is insolvent.

In the implied warranty of habitability context, insolvency means a party’s liabilities exceed its assets and the party has stopped paying debts in the ordinary course of its business. (¶¶ 89-90).  And under Pratt’s “emphatic language,” the relevant inquiry is GC’s insolvency, not plaintiff’s “recourse”.¶ 94

Sienna Court noted that assessing the viability of an owner’s implied warranty claim against a subcontractor under the “recourse” standard is difficult since there are conceivably numerous factual settings and arguments that could suggest plaintiff has “recourse.”  The court found the insolvency test more workable and more easily applied then the amorphous recourse standard. (¶ 96).

Next, the Court considered the chronological outer limit for a dissolved LLC to file a civil lawsuit.  The GC dissolved in 2010 and filed counterclaims in 2014.  The trial court ruled that the 2014 counterclaims were too late and time-barred them.

The appeals court affirmed.  It noted that Section 35-1 of the Illinois LLC Act (805 ILCS 180/1-1 et seq.) provides that an LLC which “is dissolved, and, unless continued pursuant to subsection (b) of Section 35-3, its business must be wound up,” upon the occurrence of certain events, including “Administrative dissolution under Section 35-25.” 805 ILCS 180/35-1

While Illinois’ Business Corporation Act of 1993 specifies that a dissolved corporation may pursue civil remedies only up to five years after the date of dissolution (805 ILCS 5/12.80 (West 2014)), the LLC Act is silent on when a dissolved LLC’s right to sue expires.  Section 35-4(c) only says “a person winding up a limited liability company’s business may preserve the company’s business or property as a going concern for a reasonable time”

The Court opted for a cramped reading of Section 35-4’s reasonable time language.  In viewing the LLC Act holistically, the Court found that the legislature contemplated LLC’s having a finite period of time to wind up its affairs including bringing any lawsuits.  Based on its restrictive interpretation of Section 35-4, the Court held the almost four-year gap between the GC’s dissolution (2010) and counterclaim filing (2014) did not constitute a reasonable time.

Afterwords:

Sienna Court emphasizes that a general contractor’s insolvency – not potential recourse – is the dominant inquiry in considering a property owner’s implied warranty of habitability claim against a subcontractor where the general contractor is out of business and there is no privity of contract between the owner and subcontractor.

The case also gives some definition to Section 35-4 of the LLC Act’s “reasonable time” standard for a dissolved LLC to sue on pre-dissolution claims.  In this case, the Court found that waiting four years after dissolution to file counterclaims was too long.

 

 

Constructive Fraud in IL Mechanics’ Lien Suits: A Case Study

ACHere’s one from the vault.  While dated, the case is still relevant for its cogent discussion of important and recurring mechanics’ lien litigation issues.  In Springfield Heating and Air Conditioning, Inc. v. 3947-55 King Drive at Oakwood, LLC, 387 Ill App 3d 906 (1st Dist. 2009), the First District examined the concept of constructive fraud and discussed when a subcontractor can bring alternative unjust enrichment and quantum meruit claims in a lien suit.

The plaintiff was a subcontractor who installed HVAC materials on a construction project consisting of two adjoining properties  for a total contract sum of about $400,000.  When the general contractor fired it, the plaintiff liened both parcels each for $300,000 – the total amount plaintiff was then due for its HVAC work.  The result was a “blanket lien” on the properties for a total of about $600K – double the proper amount.

The plaintiff sued to foreclose its liens and filed companion (and alternative) claims for quantum meruit and unjust enrichment against the general contractor and owner defendants.  The trial court granted the defendants’ motion to dismiss the plaintiff’s claims.  The court held that the lien claim was constructively fraudulent since it was inflated by almost two times the actual lien amount and because the lien wasn’t apportioned among the two property parcels.  The Court dismissed the plaintiff’s quantum meruit and unjust enrichment claims because it held that a subcontractor’s only remedy against an owner is a mechanics lien foreclosure action.

Held: Affirmed in part; reversed in part

 Constructive Fraud

The First District found there was no evidence of constructive fraud by the subcontractor; noting that Section 7 of the Lien Act aims to protect honest lien claimants who make a mistake rather than claimants who intentionally make a false statement or who knowingly inflates their lien.  That’s why someone must show an intent to defraud in order to nullify a lien.

While acknowledging that the plaintiff subcontractor’s lien totaled about $600K – nearly double of the amount it was actually owed – the Court looked beyond the liens’ numerical overcharge and found no additional evidence of fraudulent intent. 

This holding amplifies the First District’s Cordeck Sales, Inc. v. Construction Systems, Inc. (382 Ill.App.3d 334(1st. Dist. 2008)) ruling – a case viewed with near-Biblical reverence in Illinois mechanics lien circles – that a mechanics lien won’t be invalidated for constructive fraud simply because its inflated.  There must be an overstatement “in combination” with other record evidence that allows the court to infer fraudulent intent.  Here, there was no additional fraud evidence and the Court reinstated the subcontractor’s lien claim.

Quantum Meruit/Unjust Enrichment

The Court sustained the trial court’s dismissal of the plaintiff’s equitable counts of quantum meruit and unjust enrichment.  The general rule is that a subcontractor like plaintiff can’t recover for unjust enrichment where the entire work to be performed by the subcontractor is under a contract with the general contractor.  See Premier Electrical Construction Co. v. La Salle National Bank, 132 Ill. App. 3d 485, 496 (1st Dist. 1985). 

In such a case (no privity between owner and subcontractor), the general contractor has the power to employ whom he chooses and the owner is entitled to presume that any subcontracting work is being done for the contractor; not the owner.  Since there is normally no direct contract between a subcontractor and the owner, a subcontractor can’t claim that its work unjustly enriched the owner.

So, unless the subcontractor proves that it dealt directly with a property owner, its exclusive remedy against an owner is a statutory, mechanics lien suit.  Swansea Concrete Products, Inc. v. Distler, 126 Ill. App. 3d 927, 932 (5th Dist. 1984).  If the subcontractor misses the time deadlines to record its lien (four months, usually) or fails to timely file suit to foreclose the lien (two years post-completion of job), the subcontractor can’t then try to recover against the property owner under quantum meruit or unjust enrichment. 

Here, since the plaintiff’s contract was with the general contractor and not the owner, the plaintiff’s remedy against the general contractor was for breach of contract and its remedy against the owner was a mechanics’ lien suit.  As a result, the plaintiff’s quantum meruit and unjust enrichment claims were properly dismissed.

Afterwords: Even though the case is now several years old, Springfield Heating has continued relevance in construction lien litigation because it is the First District’s most recent word on the showing a property owner must make to prove a subcontractor’s constructive fraud when attempting to defeat a lien on the owner’s property.  Clearly, a numerical overcharge isn’t enough to defeat a lien. 

The owner must show additional “plus factors” which signals  fraudulent intent by the lien claimant.  The case also further supports the black-letter proposition that a subcontractor’s sole remedy against a property owner is a mechanics’ lien suit.  This rule will always apply unless the subcontractor can prove that the owner specifically requested or induced the subcontractor’s labor and materials on the owner’s property.